Case studies · 2 Oct 2026 · By Stefano B.
Two steel assemblies: 160 hours of drafting down to 104
Two welded assemblies, 344 bodies, from STEP to cutting drawings, booklets and nesting. 35% less time, every part checked by software.
Two welded steel assemblies from the same project. Customer names are removed. All numbers are measured on the delivered files.
Result
| Manual drafting | With StepToCut | |
|---|---|---|
| Total time, both assemblies | 160 h | 104 h |
| Saving | 56 h (35%) |
Manual time is the designer's figure for the same scope done by hand.
The two jobs
| Assembly A | Assembly B | |
|---|---|---|
| Bodies in the STEP | 200 | 144 |
| Cutting drawings delivered | 139 (from 198 parts) | 127 (117 generated, 10 kept as drawn) |
| Parts with bevels | 59 | 29 |
| Booklet | 150 cells on 31 sheets | 151 cells on 28 sheets |
| Parts for two assemblies | 398 | 288 |
| Nesting | 372 parts on 12 sheets | 274 parts on 17 sheets |
Sheets are 12 × 2.5 m. Assembly B arrived with one plate drawn by hand in place of 29 bodies, so its numbering had gaps; the 10 hand-made drawings were kept untouched.
Where the time went
- Reading the model: all 200 bodies of assembly A scanned in 13 minutes: type, thickness from the geometry, material.
- Drawings: 198 drawings generated in under 9 minutes, then merged to 139 after identical parts were grouped.
- Checks: the time saved on drafting went into checking. Every drawing, booklet cell and nested part is measured against the 3D model.
What the checks caught
- 20 extra parts in one booklet revision, caught by the quantity count and fixed in the next.
- 23 drawings where a dimension sat on top of the part, moved before delivery.
- 10 thicknesses on assembly B that disagreed with the dimensions, corrected.
- 7 mirrored parts the customer needed that were missing from the parts register.
Related: how we find identical and mirrored parts · checking quantities in a DXF