Case studies · 2 Oct 2026 · By Stefano B.

Two steel assemblies: 160 hours of drafting down to 104

Two welded assemblies, 344 bodies, from STEP to cutting drawings, booklets and nesting. 35% less time, every part checked by software.

Two welded steel assemblies from the same project. Customer names are removed. All numbers are measured on the delivered files.

Result

Manual drafting With StepToCut
Total time, both assemblies 160 h 104 h
Saving 56 h (35%)

Manual time is the designer's figure for the same scope done by hand.

The two jobs

Assembly A Assembly B
Bodies in the STEP 200 144
Cutting drawings delivered 139 (from 198 parts) 127 (117 generated, 10 kept as drawn)
Parts with bevels 59 29
Booklet 150 cells on 31 sheets 151 cells on 28 sheets
Parts for two assemblies 398 288
Nesting 372 parts on 12 sheets 274 parts on 17 sheets

Sheets are 12 × 2.5 m. Assembly B arrived with one plate drawn by hand in place of 29 bodies, so its numbering had gaps; the 10 hand-made drawings were kept untouched.

Where the time went

What the checks caught

Related: how we find identical and mirrored parts · checking quantities in a DXF